Note: By default, Technicians cannot modify PMs. Only Managers can. 

Select "Look up an Asset" from the menu.

Select the Asset in question. 

Select the PM Tab for the Asset.

Select the "New PM Template".

Create the PM by starting with a Blank Template or Copy from an existing Template.

For this example, "Weekly Check" was created. The schedule is created by selecting the "Calendar" icon from the PM tab.

Click the "Add Schedule" button.

Create Schedule.

If desired, assign this PM to a team or team member.

Did this answer your question?